Direct Dial: 968-5561
Robert P. Wise
Facsimile: 968-5593
EMail: RPW@wisecarter.com
Web: www.mslawyer.com/rwise
CONSTRUCTION CONTRACT CHANGED SITE CONDITIONS
CLAUSES
_____________________________________________________
Robert P. Wise
Wise Carter Child & Caraway, PA
(c) 2000
A. The Purpose of the "Changed Site Conditions" Clause
1. History
Changed site conditions clauses exist to temper the old rule that fixed price contracts would be rigidly adhered to no matter what the consequence might be for the contractor. For example, in the Mississippi case of Groton Bridge Mfg. Co. v. Alabama & V. Ry Co., 180 Miss. 162, 31 So. 739 (1902), the court refused to grant the contractor relief although in the construction of a railroad bridge across the Pearl at Jackson he had encountered buried logs requiring removal at great expense. The Supreme Court expressed some sympathy that the "contract proved to be an unfortunate one for the appellant, resulting in disappointment and great loss, it is true". Still, the Court noting that someone would have to "bear it", and that the contractor's contract "is silent as to obstructions"that the engineers were not bound to anticipate, found that the loss for the unanticipated condition should go to the contractor. Id. at 740-741.
Such results were not only harsh on contractors, but owners came to realize that they were facing unnecessarily high bids from contractors who were building into their bids a risk premium to deal with the risk of unanticipated site conditions that an ordinary site visit could not reveal. The U.S. Court of Appeals has explained the turn to differing site conditions clauses as follows:
2. AIA Differing Site Conditions Clause
The AIA General Conditions of the Contract for Construction (A201-1997) includes a changed conditions clause entitled "Claims for Unknown or Concealed Conditions." The changed conditions clause sets forth two kinds of changed conditions that if encountered would afford the contractor an equitable adjustment of the contract sum. These are often referred to as Type I and Type 11 conditions. AIA General Conditions A201-1997 section 4.3.4 reads:
By contrast, in Shumate Constructors, VABCA 2772, 90-3 BCA § 22,946 (1990), the Board of Contract Appeals did not grant relief to the contractor who encountered asbestos because the contract documents left no inference that significant asbestos might not be present. Also, the drawings included an architect's note explaining that the the drawings were not definitive as to the amount of asbestos present and that the contractor was required to make its own survey to determine the condition and remove all asbestos encountered. Thus, the drawings put the contractor on notice of the possible existence of the asbestos the contractor was specifically charged with removing.
(b) Type 11 Condition: Unlike a Type I condition, relief for a Type 11 condition does not turn on the owner's implied or express representations in the drawings about the condition's presence. A type 11 condition is an unknown physical condition of an unusual nature which differs materially from coditions ordinarily encountered in the type of work being done. The contractor must prove for a Type 11 condition that it was an unknown, unanticipated, and unusual condition, that a reasonable site visit or the general experience of the contractor would not have revealed it, and that the condition varied from what would normally be expected in similar work.
The requirement that the contractor prove an unusual condition can be a heavy one. For example, in Shumate the Board of Contract Appeals did not grant relief for discovery of asbestos in part because it noted that asbestos-insulated pipe was not unusual in 1920's buildings. Id. at 115,198. Similarly, in Styvesant Dredging Co., 89-3 BCA § 22,222, a dredging contractor dredged up a gas cylinder from the bottom of a bay which promptly exploded on the dredge, causing extensive damage. Even so, no Type 11 equitable adjustment was permitted to the contractor because the board of contract appeals found that the contractor was dredging in a military zone where encountering dangerous debris could not be considered unusual.
(c) Hazardous Materials Clause: However, note that in the 1997 version of the General Conditions a more specific provision now exists to deal with a contractor's encounters with hazardous materials, including specifically but not limited to asbestos and PCBs. A-201-1997, Section 10.3. If the contractor encounters hazardous materials, it is required to stop work and report it to the owner. The owner's duty then is to have a licensed lab determine what the substance is, render it harmless, extend the contract performance time and allow the contractor reasonable costs for shut-down, delay or start-up. A contractor encountering unanticipated hazardous materials should first look to this section and now may not need to use the differing site conditions clause under these circumstances.
B. Contractor's Right to Rely
The contractor can not rely on differing site conditions clauses to shift the risk to the owner or government in every case where an unanticipated adverse site condition is encountered. There are limitations. First, the clause applies only to conditions that existed when the contract was executed, not to those that may later develop during performance. Second, the unanticipated condition must be a physical condition, not an intangible impediment such as a denial of access to the work site due to the interference of a third party. After all, differing site conditions clauses are meant to shift the risk to the owner or government only those physical risks existing at the time of contract that otherwise could have affected the bidding, before any contract performance began. Olympus Corp., 98 F. 3d at 1317.
Thus, for example, in Olympus Corp. the contractor signed the contract to perform work on an industrial site and a month after the issuance of the notice to proceed encountered unanticipated contaminated soil hindering its work. The soil became contaminated when an independent contractor operating the plant accidentally cut an underground oil pipe in the plant yard. Soon after that the contractor discovered the contaminated soil, he also was locked off the site entirely for almost two months due to a strike of the plant's employees. The contractor therefore sought an equitable adjustment under the differing site conditions clause.
The Federal Circuit reviewing the case refused to recognize relief for the contractor. The court noted that neither the oil pipe break nor the strike locking the contractor off the site yet existed at the time the contractor signed the contract. Since those conditions arose during contract performance and did not exist when the contract was made, they did not qualify the contractor for relief under the differing site conditions clause. Further, the strike represented an interference in the contractor's work caused by a third party and was not a physical condition at all. Therefore again the differing site conditions clause had no application because the conditions arose during performance or were not physical conditions. Olympus Corp.,98 F. 3d at 1318.
C. Notice
It is very important to note that the differing site condition clause requires that the contractor leave the site of the condition undisturbed while he gives prompt notice to the owner of the discovery of the unanticipated condition. The AIA clause requires that notice be given within 21 days of the first observance of the condition. The notice period in necessary to allow the owner's architect to make its own investigation of the condition to see if an equitable allowance is justified. See AIA A201-1997 section 4.3.4 recited above. Although giving written notice is important to document one's rights, the AIA General Conditions permit the contractor to give oral notice of the differing site condition to the owner. Further, the owner will be required to prove it was prejudiced by any lack of notice. Shumate, 90-3 BCA § 22,946 at note 14.
D. Contractual and Tort Remedies
Even if there is no differing site conditions clause in the contract, the contractor may be able to achieve an equitable adjustment under alternative contractual and tort theories. Relief may be due for the contractor if the owner misrepresented the condition of the site, the plans and specifications were defective in that they should have but failed to account for the condition, or the owner failed to disclose his superior knowledge of a hidden condition on the site.
2) that is material or significant;
3) a failure to exercise the degree of diligence and care that is generally expected from a similarly situated party;
4) reasonable reliance on the misrepresentation or omission by the injured part;
5) that such reasonable reliance was the proximate cause of damages suffered by the injured party.
E. Conclusion
Differing site conditions clauses are now included in the general conditions for construction of the AIA and other form contracts to temper the old common law rule that stuck the contractor with a fixed price no matter what unanticipated, costly conditions he might encounter during the work, and to discourage bids inflated by an exaggerated risk premium. The unanticipated differing site conditions that can result in an equitable adjustment under the clauses include a Type I condition resulting from the implication of the drawings and specs that the condition, which differs materially from what was shown, does not exist. Relief will be given for a Type 11 condition if the condition was unusual and differed materially from those conditions ordinarily encountered in the type of work performed. If the unanticipated condition involves the discovery of unanticipated hazardous materials, the contractor with an AIA form contract may not need to resort to the differing site conditions clause, but may be able look to the more specific hazardous materials clause for relief. The differing site conditions clauses do not afford relief for unanticipated conditions or events that might occur during performance, only for physical conditions existing at the time of contract. It is very important that the contractor provide timely notice of the discovery of the condition, which is not more than 21 days in the AIA contract. Also, if there is no differing site condition clause in the contract for the contractor to rely on, he may look to the alternative remedies afforded by the owner's implied warranty of the plans and specs or to the tort of negligent or intentional misrepresentation. An owner's failure to divulge to the contractor his superior knowledge of a hidden condition may also justify an equitable adjustment for the contractor.